    PROJECT INTRODUCTION
    Lingang Special Area East 9 Financial City
    The 105 Community Finance East 9 Project in Lingang New Area is located on the north side of Dishui Lake in Lingang New Area, covering an area of approximately 145000 square meters and a total construction area of 740000 square meters. It will be developed into a financial innovation headquarters bay area that integrates high-end business offices, five-star hotels, commercial complexes, residential areas, culture, and more. The 100 meter tower is constructed for commercial and office purposes.
    施工情况
    施工类型
    抹灰
    施工面积
    290000
    施工时间
    2023.12-2024.9
    人员配置
    一台机器搭配2个大工
    砂浆供应方式
    柱塞泵
    施工平均效率
    350㎡/台/天
    施工最高效率
    400㎡/台/天
    机器人台数
    4-6
    垂平检测合格率
    98.70%
    空鼓检测合格率
    99.53%